Project Update 6
During 2018, the Trust Board was pleased to confirm the Master Plan for significant development of new, purpose-built facilities, and enhancement of current facilities, on the Shore Road Campus and Pakuranga Campus.
This is part of a series of regular Project Updates to keep you informed of our progress.
Pakuranga Campus
The internal refurbishment of the Chapel is now complete and ready for students to attend services this term. There is some work yet to complete with the planned addition of a toilet at the rear entrance of the Chapel. An official opening of the Chapel will take place in March. Look out for an article in the next Piper with the history of the Chapel and the background to the refurbishment work.
With the return of the boarders to Bruce House at the start of term, the youngest male boarders, who are housed in the Bruce House Quad, were delighted to discover that their ablution and showering facilities have had a makeover! With the bathrooms having originally been installed in 1959, the latest makeover was well-received by the boys!
To facilitate future campus development, four relocatable classrooms have been installed, with two placed in the vicinity of the Jack Paine Centre and a further two near the Science Block. With the return of the students, these are now in full use.
If you have any questions or would like more information, please send an email to masterplan@saintkentigern.com